Short History   .   Nuh Çimento – Then & Now
 

2008: The investment of the Treatment Sludge Drying Plant with capacity of 250 t/day was started in 2008 and completed and put into service at the end of the year.

2008
   

2008: Capacity of production of clinker was increased to 4.400.000 ton/year in 2008.

   

2007: It was invested for desinalization of salt water in order to meet increased water requirement in port of Nuh Cement in 2007 and by increasing the capacity in 2008, it is supplied to water production 400 m3 in hour, 200.000 m3 in month on the average.

2007
   

2006: The investment of 4th cement mill with a capacity of 320 t/h was started in 2006 and scheduled to be completed in 2007.

2007
 
2006
 

2005: In 2005, the investment of building up 4 silos was started and completed in 2006.

2005
   
2004: Total capacity increased to 4.100.000 tones/year by adding the III. Klinker Production Line with 2.000.000 tones/year. The harbor line which was previously 250 m expanded on to 595 m by lengthened first 200 m and then 145 m,
2004
   
2002: Trass Plaster Storage unit with 400 tones/hour started to run,  
   
2001: XRF, XRD, and TG-DTA/DSC devices started to use,
   
1999: Multipurpose unloading crane with a capacity of 650 tones/hour started to run,
1999
   
1996: Ship-to-coast project with 1.000 tones/hour capacity and automatic ship loading system,
1996
   
1995: One LM 16.2 coal grinder started to run. The capacity of II. oven line increased to 3.000 tones/day by precalcinating it with ACT-Pasec system,
   
1994: Trass grinder with 125 tones/hour capacity started to run. Gammametrics on-line analyzer started to run,
   
1993: The capacity of two cement grinders increased to 140 tones/hour OPC by the combi-grinding method,
   
1991: Crusher with a capacity of 1.500 tones/hour. A pre-homogeny facility with 50.000 tones capacity established,
1991
   
1990: The capacity of I. oven line increased to 120 tones/day by precalcinating it with ACT-Pasec system,
1990
   
1987: A cement grinder with 180 tones/hour capacity established,
1987
   
1983: Two LM 16.2 coal grinder built and upgrading the fuel system,
1983
   
1974: II. Oven line with a capacity of 400.000 tones/year built which increased the production capacity to 800.000 tones/year,
1974
   
1971: Port built onto the factory front field,
1971
   
1969: I. oven clinker production line with 400.000 tones/year and clinker grinding facilities established,
1969
   
1968: Factory foundation was laid,
1968
1966: Factory foundation was laid,
2006
   
1966: Company was established,