From Past to Present
1966 – Foundation of the Company
Factory Groundbreaking
1969 – Opening of the Facility
Establishment of 1st Furnace Clinker, Production Line Clinker and Grinding Plants
1971 – Scaffold Construction
Scaffold Construction in Factory Preliminary Field
1974 – 2nd Furnace Line
Construction of 2nd Furnace Line with a Capacity of 400.000 Ton/Year with an Increase in the Production Capacity to 800.000 Ton/Year
1983 – Coal Mill and Renewal
Construction of Two LM 16.2 Coal Mill and Performance of Fuel System Renewal Works
1987 – Cement Mill
Establishment of Cement Mill with a Capacity of 180 Ton/Hour
1990 – Capacity Expansion
Increase of Capacity of the 1st Furnace Line to 120 Ton/Day through Precalcination with ACT-Pasec System
1991 – Homogenizing System
Establishment of Cracking System with a Capacity of 1,500 ton/hour and Preliminary Homogenizing System with a Capacity of 50,000 Tons
1993 – Mill Capacity Expansion
Increase of Capacity of Two Cement Mills to 140 Ton/Hour By Means of Combi-Grinding Method
1994 – Trass Mill
Commissioning of a Trass Mill with a Capacity of 125 Ton/Hour and Gammametrics Online Analyzer
1995 – Capacity Expansion of the 2nd Furnace
Commissioning of LM 16.2 Coal Mill and Increase of Capacity of the 2nd Furnace to 3.000 Ton/Day
1996 – Automatic Ship Loading
Startup of Forwarding Ashore Project and Automatic Ship Loading System with a Capacity of 1.000 Ton/Hour
1999 – Commissioning of Discharging Crane
Commissioning of a Multi-Purpose Discharging Crane with a Capacity of 650 Ton/Hour
2001 – Integration of New Equipment
Putting XRF, XRD and TG-DTA/DSC Devices into Use
2002 – Trass Plaster Stockhole
Commissioning of a Trass Plaster Stockhole with a Capacity of 400 Ton/Hour
2004 – 3rd Clinker Production Line
Increase of Capacity of the 3rd Clinker Production Line to 4,100,000 Ton/Year and Port Length to 595 m
2005 – 3rd Clinker Production Line
Startup of 4-Compartment Cement Silo with a Capacity of 8.000 Tons
2006 – Online Tracking of Flue Gas Data
Integration of Horizontal-Ball Cement Mill and Establishment of Flue Gas Data Online Tracking System
2007 – Port Facility Improvements
Investment in desalting salty water, capacity expansion in 2008 and monthly average production of 200 thousand m3 water
2008 – Capacity Expansion of Clinker
Increase of clinker capacity to 4,400,00 ton/year and commissioning of Sewage Sludge Drying Plant with a Capacity of 250 ton/day
2010 – Modernization Works
All rotary furnace electrofilters are turned into bag-type filters in scope of the modernization investment for filters.
2012 – Waste-Heat Power Generation
Increase of capacity of sea-water desalting plant to 600 m3/hour and commissioning of RDF (Refuse Derived Fuel) Feeding System and 18-MW Waste-Heat Power Generation Plant